Only 16 percent of construction of Kathmandu-Terai expressway completed in past four years

KATHMANDU, July 31: The Kathmandu-Terai/Madhes Expressway has achieved only 16.10 percent of the overall physical progress of the construction works.
alt=
By Republica

KATHMANDU, July 31: The Kathmandu-Terai/Madhes Expressway has achieved only 16.10 percent of the overall physical progress of the construction works.



According to Nepal Army (NA), which has been entrusted with the responsibility of constructing the strategically important infrastructure, only Rs 25.39 billion has been spent as of Friday compared to the total estimated cost of Rs 175 billion for the construction. The infrastructure witnessed an additional work of 5.10 percent in fiscal year 2020/21.


Related story

Kathmandu-Terai Fast Track project sees 26.14 percent progress...


Out of the 72.5 km long expressway, labeling has been done on about 90 percent of 44.1 km road. Similarly, contracts have been awarded to construct bridges that have a total length of 10.59 km. As of now, preliminary works for the construction of three tunnel ways in Mahadev Tar, Dhedre and Lendada have been started.


A report of NA shows that the constructions of access sub-ways and bailey bridges are underway. Out of 5,172 ropanies of the acquired land, owners of 4,745 ropanes have been paid compensation.  


NA took over this national pride project popularly known as 'Fast Track' in 2017. The mega highway project will connect Nijgadh of Bara to Kathmandu. Although the project was originally expected to be completed by 2024, the deadline is set to be deferred due to slow work progress owing to various factors including the ongoing COVID-19 pandemic.


 

https://devmyrepublica.nagariknewscdn.com/shared/web/uploads/media/fast track nov 21.jpg
See more on: slow_work_progress
Related Stories
ECONOMY

83 percent construction of Postal Highway complete...

83 percent construction of Postal Highway completes in one and half decades
ECONOMY

Kathmandu-Terai Fast Track set to miss 2024 deadli...

Kathmandu-Terai Fast Track set to miss 2024 deadline, project records only 21.18 percent physical progress
ECONOMY

Madhya Bhotekoshi Hydropower Project gets new dead...

Madhya Bhotekoshi Hydropower Project gets new deadline of December 2022 for its construction
ECONOMY

Postal Highway to miss yet another deadline as onl...

Postal Highway to miss yet another deadline as only 65 percent construction completed in over a decade
Editorial

Blacklist Shailung Construction

Blacklist Shailung Construction

Trending

Top Videos

Bold Preety willing to fight for her musical career

Awareness among people on heart diseases has improved in Nepal’

Print still remains the numbers of one platform

Bringing home a gold medal is on my bucket

What is Nepal's roadmap to sage child rights